Sunday, November 16, 2008

Delay Penalty for Apartments

"Taarikh pe Taarikh, Taarikh pe Taarikh pur "apartment" nahin mila - Mila to sirf Tarikh."
Date after Date and Date after Date but didn't got the apartment. What I got was only Date?

This was one of the famous dialogue of Sunny Deol in Damini movie. Same story gets repeated in real life - There are dates after another date with no sign of Brigade Metropolis possession date.

As per my agreement the apartment was supposed to be delivered by March 2008 but now officially the project has been delayed by an year (March 2009). Officially it's an year but technically it's two year. I booked the apartment in Pre-Launch offer and was informed by Brigade marketing executive that hopefully we will launch the apartment in next 2 months and you should get the apartment in next 2 years. Ok, it was my first apartment and I was a fool who fell into those sugary words.

Last official communication (mail & letter) from Brigade was in Sept 2007 that project has been delayed for 3 months due to shortage of cement, sand and labour. Since then there has been a silence from Brigade Executives and there is no further official clarification as why the Project has been further delayed? Now the
forums and word of mouth has become source of "official" communication channel.

I must admit that though Brigade has delayed the project for an year but Brigade was "kind enough" to pay 3 Rs/sq ft as delay penalty with number of "if "and "else " clause.
What is the impact of this delay on our pocket?

  • I'll continue to live in a rental property for an year. If the rent in Whitefield is 10-12 Rs/ sq ft then I loose 120-144 Rs/sq ft in a year.
  • I'll continue to pay Pre-EMI and will not get tax benefits.3) In last one year Property registration cost, BESCOM/KPTCL and other payment to the different government offices may have increased which will make a bigger hole in the pocket.
  • If inflation is 10% then I'll be paying almost 10% more for buying interiors and electrical appliances for the apartment.
  • If you have spent 10 min. everyday for an year posting e-mails on different forums , reading blogs, writing mails to Brigade, following up on response, visiting Brigade office & Metropolis site to check the possession date, browsing through lawyers & Consumer forum sites, researching on the process of legal action for delay and compensation then you have spent close to 61 hrs or roughly 8 days of effort/year. You have lost 8 days of salary due to delay in possession date.
  • Have you added cost of mental agony? My dad asked me when are you coming to India? I replied the Brigade Metropolis apartment is getting ready in Oct 2008 and I will be in India that time for registration and Interiors. At every new milestone I kept assuring him now this is the final date and there won't be any postponement and I was wrong each time.
The date shifted to Dec 2008 and now it's Mar 2009.
  • If your office is in Whitefield and you are forced to continue living at some other place in Bangalore because the Metropolis apartment is not ready then add the cost of fuel and commute to Whitefield.
  • If you had plans to get your kids admitted to some school in Whitefield in 2008 but has to temporarily get him/her admitted in some other school in your current neighborhood then add the admission cost of that school.
If you add total cost then it comes to minimum of 350 Rs/sq ft but what is Brigade paying 3 Rs/sq ft or 36 Rs/sq ft (Annually) that too comes with number of "If" and "Else" clause.

  • There is a grace period of XX months before the delay penalty starts. No official date announced till now, only response is "it will be as part of the agreement".
  • If you have opted for some modification in the apartment then you will not be eligible for delay penalty. It's not clear how adding an electrical point in some room can delay apartment from the owner side?
  • The delay penalty will be settled once all the payments dues are paid from owners. Why this cannot be settled with other pending payments from owners?

Is shortage of Sand, Cement and labour the real cause of project delay or this has become a habbit of Brigade?

Now let's explore whether shortage of Sand, Cement and Labour are real cause of delay. It can be partial reasons for the delay may be for few days but certainly not for an year.
If there are real shortage of resources then
  • Why did Brigade started Phase 2 booking?
  • Why did Brigade started booking of commercial areas?
  • Why did Brigade started booking of other projects (Brigade Gateway, Brigade Petunia, Brigade PalmSprings, Brigade Paramount)?
  • Why did Brigade started booking for "K" block when they didn't had even approval due to high tension wire? Finally poor owners have been requested to shift to other blocks.
It's greed, greed and greed.

If there are shortage of resources then complete projects which you have committed to the customers. The fact is that Brigade has spread their wings in different directions ,have taken payments from the owners and have delayed the projects. If you do some math Brigade is hardly getting a hit because of delay in the projects.

After taking feedback from different forums of Brigade projects it was found that even other Brigade projects were delayed for an year. They share the same pain and frustration which we are going through.
One should also take feedback from different forums and share the experiences.

Brigade Gateway - Feedback from Brigade Gateway Google group
Brigade Millenium - Feedback from Brigade Millenium Yahoo group
Brigade Gardenia - Feedback from Brigade Gardenia Yahoo group

I also request owners from different projects to share their apartment milestones. Here are the important milestones of Brigade Metropolis.

First person to book the Brigade Metropolis apartment - July 2004
Allocation of apartment starts - June 2005
Brigade Metropolis project launch - January 2006
Request for signing the agreement - Started in January 2006 but very few people got request but majority of the people got started getting requests after April 2006.
Tentative Possession Date - Few blocks in Jan 2009 and few in Mar 2009 (note - this is still tentative)

I can see lot of cocked eyebrows asking whether Brigade is building Taj Mahal in 4 years? Brigade has failed to meet each and every milestones from apartment allocation to signing the agreement. Umm, I may be wrong there was one milestone which they met every time. I've received bi-monthly requests for payments on time every time.

Delay has now become a habit of Brigade. When I move around in the city, I see the advertisement on Billboards "Upgrade to Brigade". Now owners have started questioning why should we "Upgrade to Brigade"? Is it because you delay the project for an year and then you pay 3 Rs/sq ft as compensation that too with number of clauses.

It's high time that owners of delayed projects should come forward , unite themselves and fight for their rights. Builders take people for the ride because we allow them to take us for the ride.

Read below news on compensation for late deliveries.

Source - TOI
Builders should compensate for late delivery of flats


Many property aspires buy an under-construction flat for the convenience of slab-wise payment and lower rates. But is it such a good idea? A Mumbai consumer says her flat’s possession has already been delayed by six months. Like her, scores go through the harrowing wait for possession when housing projects-even those of reputed builders-get delayed unexpectedly. To add to their woes, consumers complain that builders rarely offer compensation, leave alone actually doling it out.

Kirti Bhatt of Ahmedabad’s Consumer Education & Research Centre, says: "In case of delay, the builder is liable to refund the amount paid with interest (for the period of delay) as there has been a breach of contract." Bhatt says Gujarat Ownership Flats’ Act, 1973, for instance, mandates builders to mention the possession date in the agreement. "Default would attract penalty under both Consumer Protection Act and the Flat Act," says Bhatt. Some states have such acts in place to protect the common man, as "housing is a state subject". Maharashtra has a similar regulation under Maharastra Ownership Flats’ Act (MOFA), 1963, says Mumbai consumer activist Jehangir Gai.

Now, consider the financial implications of delayed possession. A Mumbai consumer who was promised his flat in June 2007 says, "My agreement document clearly says that in case I intend to return the flat over delayed possession, the builder will refund the original amount with 9% interest." However, he calls this an impractical solution. "Prices have more than doubled since we booked the flat, so giving it up for just 9% interest does not make sense." Besides, he says, the interest rate on borrowed money has seen a steep rise. During the unfortunate wait, buyers lose out in other ways too. One, if they don’t own another property, they have to stay put in a rented place.

Two, if they have secured a home loan for the flat, its repayment schedule is treated as pre-EMI (equated monthly installment) till the buyer gets the property’s possession. A buyer is entitled to tax rebate under sections 24 (b) and 80 (c) of the Income-Tax Act 1961, after securing possession of the property and thus commencement of EMI. Till then, he gets no tax relief on the pre-EMI.

Vinod Sampat, advocate and president at Cooperative Societies’ Residents and Users Association, however, draws attention to a ruling that may lend hope to consumers. In May 2007, National Consumer Disputes Redressal Commission upheld a Goa State Redressal Commission order directing a real estate developer to give alternate premises of similar dimensions and in the same locality to the complainant (buyer). This, along with 18% interest per annum, on Rs 1,84,000 paid by him, from August 1991-the required possession date. Alternatively, the builder was asked to pay three times the purchase amount to the buyer-Rs 5,52,000-within 30 days of the order. Sampat adds, "Suppose I had booked a flat for Rs 20 lakh and now it’s worth Rs 50 lakh, I’m eligible for the original flat or alternatively a similar flat in the neighboring area, irrespective of price... When anyone approaches the court (for deficiency in service), its ruling is binding (on the builder)." Sampat also advises filing of a criminal case against the builder for offenses of nuisance and criminal breach of trust.

The reason builders are lackadaisical about compensation, say consumer groups, is because there is no real estate regulator yet. The only recourse available to consumers then, it appears, is approaching the courts. Bejon Misra of Delhi’s Consumer Voice, however, says: "A consumer doesn’t want to get into a legal tangle and just wants his flat in hand. Builders take advantage of this helplessness. " Misra adds, "There is a great need for government regulations for builders in terms of both quality and good practices... Due to the strong influence of property developers within policy-making bodies, a regulator (for the sector) is not coming into force." Mofatraj Munot, former president at Maharashtra Chamber of Housing Industry, however, assures: "The Centre is trying to put in place a regulator. It is in the offing."

Time and again, consumer organizations have warned against purchasing an under-construction property. This advice is all the more pertinent today because delayed housing projects are an unfortunate reality.

Vinod Sampat, president of Cooperative Societies’ Residents, Users and Welfare Association, seconds that housing projects are going slow at the moment, and says, “In this situation, the consumer is literally helpless, especially if a certain portion is paid in cash. But for the white component at least, he can file for deficiency in service on the builder’s part in a consumer court.’’

For now, a consumer court is the only redressal recourse in real estate disputes over delayed possession, quality of construction, and such others. That’s because, despite several representations from consumer groups, the critical sector continues to languish without a single-point regulator. (Things are a lot different in the developed world. Builders in the UK, for instance, even offer a 10-year warranty and insurance cover on property, says consumer activist Arvind Shenoy.)

Since housing is a state subject, each frames its own policies. As an official in the ministry of urban affairs says, “It is (to be) dealt with by the concerned state governments.’’

Bejon Misra of Delhi’s Consumer Voice, however, insists that there is an urgent need at the Central government level to bring in a strong mechanism for the sector. “This has not happened despite promises from the government.’’

A step in this direction was made by the Maharashtra government early this year with the proposed Maharashtra Housing Sector Regulatory Commission Act 2008, which stipulates the formation of a dispute redressal committee. However, it is yet to be passed.

Currently, Maharashtra has the Maharashtra Ownership Flats Act, 1963. The Act mandates a builder to provide 9% interest on the total amount paid for the flat in case of delay, says consumer activist Jehangir Gai. Then, Gujarat has its Gujarat Ownership Flats Act, 1973. Not all states, though, have such an Act in place. The National Capital Region (metropolis areas around New Delhi) does not have one, says D L Desai of Builders’ Association of India.

At an individual level, most property buyers remain reluctant to move consumer court over a dispute. Like, this Mumbai resident who has been waiting for a year-and-ahalf for his flat — without being offered any compensation. As reported earlier in these columns, a delayed housing project is a financial strain in other ways too. The Mumbai consumer, for instance, continues to shell out the EMI (equated monthly instalment) on his home loan even as he pays rent on his temporary accomodation. And, since he is still to secure the flat’s possession, he is not entitled to income-tax rebate under Section 24 (ii) of the Income-Tax Act, 1961. Certified financial planner D Sundararajan, though, says after securing possession, the interest portion on the loan paid before possession will be adjusted over the next five years, subject to a limit of Rs 1.5 lakh. If a property is in a joint name, both holders are entitled to the amount, which works out to Rs 3 lakh.

9 comments:

  1. I also had a similar bad experience with Brigade. I booked an apartment in Brigade Metropolis in October 2004. They delayed so much and their officials were making false promises and giving false date every time I meet them. The apartment layout is also too bad. In1960 Sq feet, they created small rooms. I doubt whether they are giving the actual size for what we are paying.

    ReplyDelete
  2. it's shame that greedy builders are made more greedy by people like you who pay huge pre plan deposits and regular EMI. builders become inefficient and lazy. Builder must ask for 25% cash before handover and rest on day of completion.

    ReplyDelete
  3. Manish,
    Paying 25% at the time of booking and rest at the time of handover is an ideal case. Wish it was like that. Construction industry requires large capital for the construction of buildings. Unless Builders are sitting on huge cash they may not be able to even complete the construction. However, the ideal way should be construction based payment. e.g You construct 5 floor and take 20% payment, You do flooring and woodwork take 10% and the list goes.

    Unfortunately in the seller market builder dictates the agreement and they go for Installment based payment.This becomes an issue when project gets delayed. Owners continue to pay monthly installment and builders continue delaying the project.

    ReplyDelete
  4. Saw this thanks, will never buy Brigade, will forward to all my friends too

    ReplyDelete
  5. Seems Brigade is one among them. I am experiencing worse treatment from Apple A Day properties private limited in Cochin, Kerala. Project hand over is delayed by 23 months already and construction is far from over. All the builder is offering a compensation of Rs2/- per square feet per month and a new target completion date. Pathetic!

    ReplyDelete
  6. Same is the issue with Royal Palms, Mumbai. They are bloody cheats. We booked a condominium in 2005. The builder took 80-90% of the flat amount and then stopped work. The possession was promised in April 2008 according to the agreement along with all amenities and furniture.
    The building still lacks basic amenities like lift, proper electrical wiring, tap/sanitation fittings, leakages etc. And no furniture has been given. Now the builder asks us to take possession and give the remaining amount + maintenance charges since April 2008.
    We have lost out on other investment opportunities and now we are at complete loss. Plus we still haven't got possession of the property.

    ReplyDelete
  7. Skyline's Beverly Park in Bangalore North. Its the same story. Possession date was June 2009. Looks like it will be delayed by 3 years.

    ReplyDelete
  8. What is the rate per square foot, I should ask builder to mention in agreement clause in case of delay in possession of flat. He is offering Rs 5 /sqft. Is this rate reasonable. I will be paying pre EMI which will be almost 5 to 6 time what he is offering. Is there any Act for Karanataka to fix compensation on delay in possession.
    -|- Dev

    ReplyDelete
  9. I am booking a flat and want to know what is the Flat Act in Karanataka for compensation

    Builder is proposing Rs 5 / sqft area. Is this amout ok? I do not find it ok compared to the pre EMI i will have to pay to the Bank. Please advice.

    ReplyDelete